South Street ADA Improvements

Project Information


City Project No.:

  • 19-21-M

Description:

  • This project includes sidewalk replacement in order to provide accessibility for persons with disabilities on South Street.

Status:

  •  Construction

Project Funding:

  • Community Development Block Grant (CDBG)

Schedule:

  • Construction was started on January 16, 2023 with an estimated completion in Spring 2023.


Scope of Work

This project will accommodate and provide accessibility for persons with disabilities on South Street from Oldtown Road to Industrial Boulevard at the intersections of South Street and First Street, Second Street, Third Street, Fourth Street, and Franks Lane. This project includes the installation of accessible curb ramps at the aforementioned street intersections, concrete pavement repairs, the adjustment and modification of several existing inlets, and the replacement of a small retaining wall at First and South Streets.